Ontario Construction Act Remedies for Unpaid Subcontractors: Prompt Payment, Adjudication, Trusts and Liens

Ontario Construction Act remedies for unpaid trades: proper invoices, prompt payment notices, ODACC adjudication, trusts, holdbacks and liens.

Enforcing payment down the Ontario construction pyramid through statutory prompt payment clocks, notices of non-payment, ODACC interim adjudication, statutory trusts and condominium lien deadlines.

Jurisdiction
Canada
Practice area
Canada Law · Construction Law
Research engine
Canada Legal
Updated & length
23 November 2026 · 5 min read

PRIMARY AUTHORITIES EXAMINED

  • Construction Act, R.S.O. 1990, c. C.30 (Parts I.1, II, II.1, IV and VIII, § 87.3) and O. Reg. 306/18
  • Building Ontario For You Act (Budget Measures), 2024, S.O. 2024, c. 20 (Construction Act Amendments)
  • Pasqualino v. MGW-Homes Design Inc., 2022 ONSC 5632 (Div. Ct.)
  • Ledore Investments Ltd. v. Dixin Construction Ltd., 2024 ONSC 598 (Div. Ct.)
  • Ontario Dispute Adjudication for Construction Contracts (ODACC) Procedures

Prompt Payment Timelines and Notices of Non-Payment

Part I.1 of Ontario's Construction Act establishes rigid statutory cash-flow clocks triggered whenever a contractor delivers a compliant 'proper invoice' meeting section 6.1 requirements to the project owner. Once the owner pays the contractor—which the owner must do within the statutory owner-payment window absent a timely owner Notice of Non-Payment—section 6.5 obligates the general contractor to pay every subcontractor whose work was included in that proper invoice within the short statutory cascading payment window.

Informally complaining about drywall deficiencies over email or phone carries zero legal effect under Part I.1. To lawfully withhold payment from a subcontractor after being paid by the owner, the general contractor must deliver a prescribed written Notice of Non-Payment (Form 1.3) strictly within the statutory contractor-payment window, detailing the exact disputed amount and all factual reasons for non-payment. Failing to serve a timely, compliant Notice of Non-Payment strips the contractor of statutory justification to withhold funds, triggers mandatory statutory interest under section 6.9 at the higher of the contract rate or Courts of Justice Act prejudgment rate, and sets up an immediate fast-track adjudication victory.

ODACC Interim Adjudication, Enforcement and Judicial Review

Part II.1 equips unpaid trades with rapid interim dispute resolution administered by the Ontario Dispute Adjudication for Construction Contracts (ODACC) without halting work or waiting years for trial. A subcontractor still active on site may serve a Notice of Adjudication covering valuation of services, payment under the subcontract, notices of non-payment, holdback, or set-offs. An accredited adjudicator renders a written determination within the rapid statutory post-document-delivery window.

An adjudicator's determination is binding on an interim basis ('pay now, argue later'): the contractor must pay within the short statutory post-determination deadline, failing which the subcontractor gains the statutory right under section 13.19(5) to suspend further work on site without breaching the subcontract while recovering demobilization costs, AND may file the certified determination with the Ontario Superior Court of Justice under section 13.20 for immediate enforcement as a court order (garnishment or writ of seizure). Challenging an adjudication requires leave for judicial review to the Divisional Court strictly on narrow section 13.18 procedural-fairness or jurisdictional grounds—as underscored in Pasqualino v. MGW-Homes Design Inc. and Ledore Investments Ltd. v. Dixin Construction Ltd., where Divisional Court confirmed that procedural fairness must be respected but substantive merits errors do not warrant setting aside interim awards.

Statutory Trusts, Holdbacks and Condominium Lien Preservation

Beyond prompt payment, Part II of the Construction Act impresses all funds received by a general contractor from an owner on account of a contract price with an immediate statutory trust under section 8 for the benefit of unpaid subcontractors and suppliers. Diverting owner-paid project monies to other sites or general corporate overhead while leaving the drywall trade unpaid exposes not only the corporate contractor but also individual directors, officers, and controlling minds to personal breach-of-trust liability under section 13—a liability that survives corporate bankruptcy under BIA section 178(1)(d).

Preserving in rem lien security requires strict compliance with Part V deadlines and condominium-specific registration mechanics. Under section 31, a subcontractor's lien expires after the statutory preservation window measured from the earliest of publication of a certificate of substantial performance, completion/abandonment/termination of the prime contract, or the subcontractor's last supply of services or materials—followed by a mandatory statutory perfection window under section 36 to issue a statement of claim and register a Certificate of Action. On a Toronto condominium development, if the condominium declaration has already been registered prior to lien preservation, the lien must be registered properly against common elements and individual units under Condominium Act coordination rules (with pre-registration notice rules for home buyers where applicable), though an owner or contractor may vacate the registered lien from title under section 44 by posting full lien value plus statutory security for costs into court.

Statutory Transition Rules and Recent Ontario Amendments

Practitioners must always verify which statutory version governs a multi-year construction project before calculating deadlines or advising on annual holdback release.

  • Under Construction Act section 87.3 transition rules, applicability of modern prompt payment, adjudication, and extended lien timelines hinges on the date the prime procurement process commenced or the prime contract between the owner and general contractor was entered into—NOT the date a lower-tier subcontract was signed.
  • Recent Ontario legislative reforms (including the Building Ontario For You Act (Budget Measures), 2024 amendments to the Construction Act) introduced modernized mandatory annual holdback release mechanisms, broadened adjudication scope, refined proper-invoice deeming provisions, and consolidated holdback rules, each governed by tailored statutory transition provisions.
  • Because liens, trust claims, and ODACC adjudications run on independent legal tracks, pursuing adjudication never pauses or extends strict statutory lien preservation and perfection clocks under sections 31 and 36.
FILE PREPARATION

Construction Law checklist for Canada.

  • Verify the exact execution date of the prime contract and commencement of prime procurement under section 87.3 to confirm governing Construction Act transition rules.
  • Request confirmation under section 39 right-to-information demands regarding owner payments made to the contractor, contract price, and holdback balances.
  • Inspect all project correspondence to confirm whether the contractor failed to deliver a prescribed Form 1.3 Notice of Non-Payment within the statutory window.
  • Prepare and serve an ODACC Notice of Adjudication swiftly while simultaneously diarizing independent lien preservation (section 31) and perfection (section 36) cutoffs.
  • Check land registry PINs to determine whether a Toronto condominium declaration has been registered so any Claim for Lien accurately describes affected units and common elements.
  • Put the contractor's directors and officers on formal written notice of statutory section 8 trust obligations and personal section 13 liability for diverted project funds.
OFFICIAL SOURCES

Canada Legal primary repositories.

Construction Law questions in Canada.

Does starting an ODACC adjudication extend the deadline to register a construction lien in Ontario?
No. Adjudication under Part II.1 and construction lien preservation under Part V operate on completely separate statutory clocks. A subcontractor must strictly preserve and perfect its lien within sections 31 and 36 deadlines even while an adjudication is actively underway.
Can a subcontractor walk off a Toronto job site immediately when the contractor misses a prompt payment deadline?
Not automatically upon missed payment alone without risking subcontract breach. The statutory right to suspend work with demobilization cost recovery under section 13.19(5) arises specifically when the contractor fails to pay an adjudicator's determination within the statutory post-determination deadline (unless the subcontract itself grants earlier suspension rights).
Why does the prime contract date matter more than the subcontract date under Ontario's Construction Act?
Section 87.3 ties statutory transition rules to when the prime contract was signed or its procurement process commenced. Even a subcontract signed recently can remain governed by earlier statutory provisions if it flows under a legacy prime contract predating the applicable transition cutoff.
RELATED CANADA GUIDES
Professional tools. Professional judgement.

Every answer links each reference to its official text. Catalogue updated 15 November 2026.

10 free questions within 14 days, no credit card. After signing in, ask your first question. The trial starts on Quick answers, and any short answer can be turned into a full memo free.