Statutory hardship (imprévision) under Article 1195 of the Code civil
Reversing more than a century of rigid pacta sunt servanda orthodoxy since the 1876 Canal de Craponne judgment, Ordonnance n° 2016-131 enacted Article 1195 of the Code civil introducing a statutory hardship mechanism (imprévision) for private-law contracts concluded on or after 1 October 2016. Relief requires three strict cumulative conditions: a change of circumstances unforeseeable at contract conclusion, making performance excessively onerous (excessivement onéreuse) for a party, where that party did not assume the risk of such change.
Unlike force majeure, hardship does not suspend contractual obligations while talks unfold: Article 1195 expressly obliges the affected party to continue performing throughout renegotiation. If the counterparty refuses renegotiation or talks fail, the parties may mutually terminate or ask the judge to adapt the contract; failing agreement within a reasonable time, either party alone may petition the Commercial or Civil Court to revise the contract terms or terminate it on such date and conditions as the judge determines.
Contractual waivers, price-indexation traps and statutory carve-outs
Crucially for commercial drafters, Article 1195 is non-mandatory (supplétif de volonté). Business-to-business supply agreements, construction contracts and M&A share purchase agreements routinely exclude Article 1195 outright — expressly declaring that each party accepts the risk of unforeseeable economic shifts — or replace judicial revision with structured commercial hardship clauses setting objective raw-material triggers, notice periods and capped margin-sharing formulas.
Certain transactions sit outside Article 1195 by statute: following the 2018 Ratification Law, Article L211-40-1 of the Code monétaire et financier permanently excludes obligations arising from transactions on financial securities and financial contracts (including share sales of SAS/SA stock and derivatives). Practitioners must also test any unilateral exclusion clause in standard-form adhesion contracts (contrats d'adhésion) against Article 1171 Code civil and commercial significant-imbalance rules under Article L442-1 I 2° Code de commerce.
- Check the contract execution date and any express Article 1195 exclusion or risk-allocation language before initiating hardship correspondence.
- Keep performing deliveries or payments during Article 1195 renegotiation so the counterparty cannot allege prior contractual breach under Article 1217.
- Substantiate 'excessively onerous' impact with audited unit-cost margins rather than temporary market price fluctuations.
Force majeure criteria and monetary-debt exclusions under Article 1218
Article 1218 Code civil defines contractual force majeure as an event beyond the debtor's control that could not reasonably have been foreseen at contract formation and whose effects cannot be avoided by appropriate measures, preventing performance of the obligation. All three limbs — exteriority/beyond control, unforeseeability and irresistibility — are cumulative and construed strictly by the Cour de cassation.
Temporary impediment suspends performance (unless the resulting delay justifies contract termination), whereas permanent impediment terminates the contract automatically by operation of law and releases both parties under Articles 1351 and 1351-1 Code civil without damages. Importantly, settled Cour de cassation case law holds that a party bound by a pure monetary payment obligation can never invoke force majeure to excuse non-payment (genera non pereunt), and a creditor unable to enjoy a service (such as a hotel or premises closed during administrative restrictions) cannot plead force majeure to escape paying rent where the supplier itself remains ready to perform.
Interaction with good faith, unilateral termination and summary litigation
Even where a contract waives Article 1195, the mandatory duty of good faith (bonne foi) in Article 1104 Code civil remains unwaivable. While good faith does not empower French judges to rewrite core contract prices where Article 1195 was validly waived, courts scrutinise whether a dominant counterparty abused refusal to adjust delivery schedules or exercised unilateral termination clauses (Article 1226) opportunistically during a supply shock.
Parties confronting severe cost inflation or supply-chain disruption should pair formal contractual notices with documented mitigation efforts (alternative sourcing attempts, supplier correspondence and cost audits) so that any subsequent commercial court action — or interim summary proceeding (référé) to preserve deliveries — rests on verifiable evidence of proportionality and good faith.